HixtoryBETAView on the map

EventLao People's Democratic Republic

The Nam Theun 2 Hydropower Plant Starts Operating

2010 · Lao People's Democratic Republic · Nam Theun River (Nakai Plateau)
Today: Khammouane Province, Laos

In 2010 the 1,070-megawatt Nam Theun 2 plant, built in central Laos, began commercial operation, and most of its electricity is sold to Thailand.

What happened

In 2010 a large hydropower plant opened in central Laos. Most of the electricity made there is sold to Thailand. Laos hopes to grow the country with the money it earns this way.

More detail

Under review

Why it happened

Nam Theun 2 is the representative project of Laos's policy of building large hydropower plants to earn foreign currency. Twenty-seven parties, including the World Bank and the Asian Development Bank, provided funds.

It is also a project that drew long debate in the international community over environmental and resettlement issues.

What happened

The plant did test generation in mid-2009 and then began commercial operation in 2010 (some sources say April). Its capacity is 1,070 megawatts, of which 1,000 megawatts are exported to Thailand and 70 megawatts are used within Laos.

The total cost differs from source to source, from 1.25 to 1.5 billion dollars.

What came of it

Laos expected to earn about 2 billion dollars from this project in taxes, dividends, royalties and so on. The World Bank's social and environmental program ended on 31 December 2017.

Laos continued its goal of becoming the "battery of Southeast Asia," and projects such as the Xayaburi Dam followed later.

Laos and Thailand concluded several government-to-government memoranda of understanding, and Nam Theun 2 is the largest project developed under them. The promise of electricity exports made the large project possible.